Radiological risk reduction activities include establishing a new mine floor in some areas
WIPP's new hybrid (diesel/electric) bolter
Concrete placements for the Interim Ventilation System
Supplemental Ventilation System fans arrive at WIPP

WIPP Update

July 9, 2015

Supplemental Ventilation System Arrives at WIPP

Sections of the new Supplemental Ventilation System (SVS) arrived at WIPP this week. The SVS is designed to increase the total amount of air supplied to the underground. The fan assembly underwent factory acceptance testing last week and arrived at the WIPP facility early this week.  The fan and associated equipment will be transported to the WIPP underground in four pieces where it will be assembled by WIPP personnel.  Once operational, the 151 horsepower electric fan will be positioned near the primary air intake shaft where it will be used to draw approximately 130,000 cubic feet per minute (cfm) of surface air into the underground. Used in conjunction with the Interim Ventilation System (IVS), the SVS will increase the air supplied the underground to approximately 180,000 cfm.

SVS shipment arrives at WIPP
WIPP Employees unload sections of the SVS early this week at the WIPP Facility

Under the current configuration, one of the three 860 series fans is operated at a time, pulling air through the underground and exhausting it through High Efficiency Particulate Air (HEPA) filters.  The new SVS is designed to work in combination with the IVS and the current ventilation system to augment these fans, increasing the overall airflow in the underground necessary to allow operation of additional pieces of equipment.  WIPP employees continue to work safely to restore the WIPP facility to full operations.

Next WIPP Town Hall Meeting Scheduled August 6

The City of Carlsbad and DOE will co-host its Town Hall meeting featuring updates on WIPP recovery activities. The meeting is scheduled for Thursday, August 6 at 5:30 p.m. Location: Carlsbad City Council Chambers, 101 N. Halagueno Street. Live streaming of the meeting can be seen at http://new.livestream.com/rrv/.

Reports and Plans

 
Recent

AIB Phase II Report on the February 14 Radiological Event

AIB Phase II Investigation Summary Slides

Older

AIB Investigation Report on the February 5 Fire

AIB Investigation Summary Slides

AIB Phase I Report on the February 14 Radiological Event

AIB Phase I Investigation Summary Slides

Office of Environmental Management Corrective Action Plan for Fire Event

Office of Environmental Management Corrective Action Plan for the Radiological Event

CBFO Corrective Action Plan for the Fire and Radiological Events

NWP Corrective Action Plan for the Fire and Radiological Events

Technical Assessment Team Report

Supporting Documents

Supporting documents for the AIB and TAT reports


Did you know?

WIPP has made significant progress in its recovery efforts

On September 30, 2014, the Waste Isolation Pilot Plant (WIPP) Recovery Plan was issued. It outlines the necessary steps to resume limited waste disposal operations in the first quarter of calendar year 2016. 

Several of the steps have been completed and WIPP is making good progress in its recovery efforts.



For more information about the WIPP Recovery Plan, see the Plans and Reports page.

CBFO JOB OPPORTUNITIES